Reconstruction of the CC Banja Luka, after justified giving up the previous project with the company Vamed at the head, started by the Government in April 2008. In that decision the Government has clearly stated that the reconstruction of the CC Banja Luka is one of the most important projects in RS. Project Leader, together with the Government of the RS, are the Ministry of Health and Clinical Center of Banja Luka, as an operational body, and CC neds to do a complete design and execution of works, under the auspices of the Government of RS. At this point, since there was no one document that could be used for this purpose, it was necessary to make primary documents, first of all, plan of reconstruction and protocols about competence. The plan of reconstruction defines the phase of reconstruction, the method of control by the competent Ministry of Health and the Ministry of Finance. RS Government adopted the decision to award the first initial 20 million BAM of funds for this purpose, in order to start this complex work

Up to now has been done:
– Urban Development of the technical conditions for the reconstruction of water supply and sewerage system of the CC of Banja Luka
– Making the execution of the project to build a new and reconstruction of existing water systems and sewerage of the CC of Banja Luka
– The agreement on the UTU for the reconstruction of external water and sewerage system of the Clinical Centre of Banja Luka
– Execution of works on construction of new and reconstruction of the existing water system of the CC of Banja Luka
-Execution of works on construction of new and reconstruction of the existing sewerage system of the CC
– Supervision of construction of new and reconstruction of the existing water system and of the CC-Banja Luka
– Development of project documents for the renovation and reconstruction of part of ground floor building maternitea 2A
– Purchase of furniture for Property maternitea, Clinical Center Banja Luka
– Execution of works on the adaptation of part of ground floor building maternitea 2A
– Execution of works on part of ground floor to make it bigger on the part of the Institute of Radiology 2A facility materniteaCC
– Supervision of the works on the adaptation of part of ground floor building maternitea 2A
– Execution of works on reconstruction of the flat roof of the Clinic for Infectious Diseases
– Execution of works on completion of paving and underground corridors TEB DAM-cellar (basement),
– preparation of the power of 11 lifts L11-L22 in the facilities of Maternita, Infectious clinic and TEB –
Purchasing and installation of 22 elevators for the Clinical Centre of Banja Luka,
– Supervision of installation of 22 elevators in the Clinical Center of Banja Luka,
– Funds for autopsic part of the Institute of Pathology,
– Geodetic record for scale 1:250, create digital terrain models and surveying the situation and making 1:250 scale drawings of given longitudinal profile
– Dividing into plots the soil of Clinical Center of Banja Luka,
– Development of project task adaptation and extension of the Clinical Center of Banja Luka
– Testing the concrete structures of unfinished buildings of the Clinical Centre of Banja Luka –
– Geomechanical testing of the location of office building on the plateau, close to the central medical block on Paprikovac –
– Development of urban-technical conditions for the Central medical block and south wing of the Central Medical Block of CC of Banja Luka
– Preparation of the project task for the stabilization of landslides and soil testing (New psychiatric clinic)

Making the execution of the project design and reproject of the CC of Banja Luka. Making the execution of the project for reconstruction of the Clinical Center goes to the planned schedule, and priority at this time, with the approval of the Ministry of Health and Social Welfare, is making the execution of the project of reconstruction and expansion of the Institute of Radiology in which would be placed the apparatuses according to the Clinical Center Project ” Korea II” wiil be there by the mid of this year, and production of the solutions for the second phase of the South Wing. Also in parallel with the ongoing execution of the project is the creation of a complete operating block with intensive care,
– Audit the execution of the project design and reproject of the Clinical Centre of Banja Luka. 75% of contracts is implemented. A preliminary positive report on the audit of projects was received by the auditor, by which have been acquired all of the conditions that the project in the final stages of being implemented in full
– Performance audit services project and technical documentation of the Central medical block of CC of Banja Luka. After implementation of thisContract, all documentation is submitted to the Ministry of Physical Planning, Construction and Environment and they need to submit a building permit which is necessary for the reconstruction of this building,

-Payment of contributions to the establishment of a cadastral survey and real estate in an amount of 0.3% of pre-calculated value of construction works in order to issue permits for construction of the Centre for radiotherapy South – Phase I of construction,
– Decision of the Ministry of Physical Planning, Civil Engineering and Ecology of RS no. 15-360-44/09 of September, the 2nd, 2009, by which was given approval for the construction of the South Wing’s CMB – Center for radiotherapy South – First Construction Phase
– Execution of works on construction of the southern wing of CMB of Clinical Centre of Banja Luka (Phase I). Construction of part of the southern wing of Phase I, which are joint investments of the Government of the RS and Euromedica, running a good pace in line with the dynamic plan in coordination with the contractors hired by the “EUROMEDIC and CC Banja Luka. According to last assessment, was completed more than 60% of total hard construction work, it has started deliveries of medical equipment, and it is reasonable to expect that the Center for radiotherapy, which should be first put into operation, the first patients is about to receive for radiation therapy services in early August of this year.

Professional and technical supervision of construction of new and reconstruction of existing facilities of the Clinical Centre of Banja Luka. According to our insight into the situation on site, ZIBL participates in the necessary changes of the project which are needed in the area of adaptation of the project and perform the actual conditions of supervision,
– Performance of the geodesic services on location Paprikovac – Center for Radiology,

Projects in progress:

– Planning the construction of psychiatry
– The project of rehabilitation of landslides on the site which was adopted in the spatial arrangement provided for the construction of Psychiatry
– Execution of works to repair the roof GAK
– Project Planning making better roads to Paprikovac
– Execution of works to expand and reconstruction of the Institute of Radiology,
– Design for the reconstruction of kitchen,

-Development of economic studies on the need for technical and economic reconstruction of the block and the justification of investment, and finding modalitiesof financing. Reconstruction of the power plants in Paprikovac is necessary for several reasons, one of which certainly should be pointed out deterioration of equipment that is unable to meet any need at this time and it it could not do that especially when the whole complex of the Clinical Center is on site Paprikovac and energy production in the most expensive way,
– Execution of works on construction of Phase II of the southern wing and interior furnishing of the entire southern wing, under the auspices of the Ministry of Health, which ends activities on providing the necessary resources,

– Execution of works on reconstruction of Clinical Center of Banja Luka, the operating block, intensive care, emergency medicine center, central sterilization in central block, given the size of the investment, represents the largest part of the project of reconstruction of the central block of the Clinical Center. In coordination with the Government of the RS, are carried out the activities of provision of funds , primarily through the European Development Bank, but also from other sources, in order to facilitate the smooth reconstruction of short time and unhindered completion of works, because Clinical Center must provide the function all the time, despite the reconstruction. Once the work starts, schedule of works must be strictly adhered to, for any delays call into question the primary function of the Clinical Center. Insistence on this position is supported by all entities participating in the project of reconstruction of the Clinical Center.

Mirko Stanetić, PhD, specialist
Head Director